The Bossier Schools System is one of the fastest growing public school districts in Louisiana, resulting in record student enrollment. To address the rapid growth across Bossier Parish, voters approved a $210 million bond referendum in April 2012 to build new schools and improve existing ones, better positioning Bossier Schools for the present and future and offering students a desirable learning environment.
The Bossier Parish School System is one of the fastest growing public school districts in Louisiana, resulting in record student enrollment. To address the rapid growth across Bossier Parish, voters approved a $210 million bond referendum in April 2012 to build new schools and improve existing ones, better positioning Bossier Schools for the present and future and offering students a desirable learning environment.
Phase 1 Projects (years 1-5)
Bossier City
Airline High
New wings; office addition; office, media and restroom renovations
Project Cost: $23,353,317Bossier High
Required Renovations – Electrical, Utility Service, Ceilings, Paint
Project Cost: $228,425Bossier Parish School for Technology and Innovative Learning (BPSTIL)
New Building
Project Cost: $21,798,439WT Lewis Elementary
Three 4-room wings
Project Cost: $2,007,500Legacy Elementary
Paving
Project Cost: $227,504Kingston Elementary
New 950 capacity K-5
Project Cost: $16,835,601
BENTON
Benton Elementary
Paving and drainage
Project Cost: $697,488
HAUGHTON
Haughton Middle
New Building
Project Cost: $34,943,866Haughton South Elementary
Paving, Drainage, Gym Canopy, Convert M.S. to K-5
Project Cost: $2,496,302T.L. Rodes & Platt
Paving, traffic & parking improvements; land acquisition
Project Cost: $1,763,223Princeton
Paving
Project Cost: $439,373Haughton High
Baseball Facility & Stadium drainage
Project Cost: $403,150
PLAIN DEALING
Carrie Martin
New electrical service
Project Cost: $257,807
ROAD IMPROVEMENTS DISTRICT-WIDE FOR
NEW SCHOOLS
Kingston Elementary
Turn lanes on Kingston Road, extension of Poydras StreetBPSTIL
Extension of Town Lake Blvd.New Haughton Middle School
Turn lanes on Hwy 3227
District-wide Budget
for LAND:
Kingston Elementary
Project Cost: $1,137,801BPSTIL
Budget: $653,550Jepson
Project Cost: $1,298,419Turtle Creek
Project Cost: $187,018Caplis Sligo Road Tract
Project Cost: $790,713MISCELLANEOUS DISTRICT-WIDE
Parkway High
Traffic Study
Project Budget: $34,055BAFB Bodcau Gate
Utility Improvements
Project Cost: $125,000
Phase 2 Projects (years 6-10)
Bossier City
Bossier High
Required renovations & stadium improvements
Project Cost: $3,957,518Cope Middle
C.R, band & commons, secure entry
Project Cost: $2,061,144Parkway High
12 room wing
Project Cost: $5,500,000Parkway High
Athletic field restrooms, concession & site improvements
Project Cost: $842,230Sun City
Wing
Project Cost: $2,373,417
Benton
Benton High School
New High School
Project Cost: $57,151,907Benton Intermediate
12 Room wing, Ring Road planning
Project Cost: $2,926,608
HAUGHTON
Haughton High
30 room wing & Admin building
Project Cost: $14,032,923Bleacher repairs: $284,143
Practice field paving & drainage (Improvements): $854,968
LED field lighting: $758,601
PLAIN DEALING
Plain Dealing
Site improvements & Press box
Project Cost: 730,130