5.2 Cope Middle School Wing - Complete

Slider is playing

Cope Middle School

4814 Shed Road

Bossier City, LA 71111

The new 8,000 sf wing includes a new band room, student & faculty restrooms and 4 classrooms.

Construction was substantially completed May 25, 2021, 3 weeks ahead of schedule, which allowed teachers to begin moving in before the start of summer.

Project Budget:

$2,114,149

Completion Date:

May 2021

Program Manager:

Architect:

  • Kevin Bryan

Contractor:

  • M & M Builders, Inc.

    • Low bid including alternates – $1,639,869.40 – under budget